Achievement & Milestones |
| |
Highlighting efforts made after the formation of CSEB upto January 2009 |
| |
|
February 2000 |
December 2008 |
% Increase |
| |
Thermal Generation Capacity |
1240 |
MW |
1786 |
MW |
44.03 |
| |
Hydel Generation Capacity |
120 |
MW |
137.85 |
MW |
14.88 |
| |
Total Generation Capacity (Thermal + Hydel) |
1360 |
MW |
1923.85 |
MW |
41.46 |
| |
Increase in Generation Capacity |
|
|
563.85 |
|
|
| |
No. of EHT Sub Stations |
27 |
|
62 |
|
129.63 |
| |
Length of EHT Line |
5205 |
Circuit KM |
7276 |
Circuit KM |
39.79 |
| |
No. of 33/ 11 KV Substations |
248 |
|
613 |
|
147.18 |
| |
Length of 33 KV Line |
6988 |
Circuit KM |
13095 |
Circuit KM |
87.39 |
| |
No. of 11/ 0.4 KV Sub Station |
29622 |
|
55184 |
|
86.29 |
| |
Length of 11 KV Line |
40556 |
KM |
56365.38 |
KM |
38.98 |
| |
Length of LT Line |
51314 |
KM |
94626.5 |
KM |
84.41 |
| |
Capacitor Installed |
94 |
MVAR |
934 |
MVAR |
893.62 |
| |
No. of Electrified Villages |
17953 |
|
19028 |
|
5.99 |
| |
Electification percentage |
91 |
|
96.37 |
|
5.90 |
| |
No. of Electrified Majra Tola |
10375 |
|
21542 |
|
107.63 |
| |
No. of Electrified pumps |
72400 |
|
217295 |
|
200.13 |
| |
Single Point Connections |
630389 |
|
1015105 |
|
61.03 |