Current Installed
Capacity |
|
Unit wise Installed Capacity, Date of Commissioning & Date of
Commercial Generation |
|
|
|
|
|
|
|
|
S.No. |
|
Unit No. |
Installed Capacity (MW) |
Date of Commissioning |
Date of Commercial Generation |
|
Thermal Power Stations (1786 MW) |
|
1 |
Korba East Thermal Power Station (440 MW) |
|
Power House No. II |
I |
50 |
5-Sep-1966 |
|
|
II |
50 |
16-May-1967 |
|
|
III |
50 |
23-Mar-1968 |
|
|
IV |
50 |
31-Oct-1968 |
|
|
Total |
200 |
|
|
|
Power House No. III |
I |
120 |
27-Apr-1976 |
|
|
II |
120 |
5-Apr-1981 |
|
|
Total |
240 |
|
|
|
|
|
|
|
|
|
|
2 |
Korba East, Dr. Shyama Prasad Mukherjee Thermal Power Station
(500 MW) |
|
|
I |
250 |
30-Mar-2007 |
27-Jun-2008 |
|
|
II |
250 |
11-Dec-2007 |
30-Nov-2008 |
|
|
Total |
500 |
|
|
|
|
|
|
|
|
|
|
3 |
Korba West, HasdeoThermal Power Station (840 MW) |
|
|
I |
210 |
21-Jun-1983 |
|
|
|
II |
210 |
31-Mar-1984 |
|
|
|
III |
210 |
26-Mar-1985 |
|
|
|
IV |
210 |
13-Mar-1986 |
|
|
|
Total |
840 |
|
|
|
Hydel Power Stations (138.70 MW) |
|
1 |
Mini-Mata Hasdeo Bango Hydel Power Station (120 MW) |
|
|
I |
40 |
21-Mar-1994 |
|
|
|
II |
40 |
21-Nov-1994 |
|
|
|
III |
40 |
11-Jan-1995 |
|
|
|
Total |
120 |
|
|
|
|
|
|
|
|
|
|
2 |
Gangrel Hydel Power Station (10 MW) |
|
|
I |
2.5 |
2-Apr-2004 |
28-Jul-2004 |
|
|
II |
2.5 |
29-Jun-2004 |
4-Aug-2004 |
|
|
III |
2.5 |
17-Oct-2004 |
3-May-2005 |
|
|
IV |
2.5 |
5-Nov-2004 |
23-May-2005 |
|
|
Total |
10 |
|
|
|
|
|
|
|
|
|
|
3 |
Sikasar Hydel Power Station (7 MW) |
|
|
I |
3.5 |
3-Sep-2006 |
|
|
|
II |
3.5 |
3-Sep-2006 |
|
|
|
Total |
7 |
|
|
|
|
|
|
|
|
|
|
4 |
Korba West Mini/ Micro Hydel Power Station (1.7 MW) |
|
|
I |
0.85 |
12-Jan-2003 |
|
|
|
II |
0.85 |
29-May-2009 |
4-Aug-2009 |
|
|
Total |
1.7 |
|
|
|
Other Power Stations (6 MW) |
|
1 |
Bhoramdev Co-Gen, Kawardha (6 MW) |
|
|
I |
6 |
10-Aug-2006 |
|
|
|
Total |
6 |
|
|
|
|
Grand Total (Thermal + Hydel) |
1924.7 |
MW |
|