Chhattisgarh State Power Distribution Company Limited

 

 

 

   
  Planning and Status
  Reforms  for Strengthening T&D System
  (After the formation of CSEB up to November - 2011)
  S.No. Name of Works Status as on March 2011 Year 2011-12 Status as on Oct - 2011
  Target Achievement
  1 New 33/11 KV Sub-Station 443 37 8 451
            (a) Additional 33/11 KV Power X'mers  206 25 8 214
            (b) Augmentation of 33/11 KV Power X'mers  445 30 9 454
  2 New Distribution Transformers under ND Schemes 10470 1800 676 11146
  3 Augmentation of Distribution Transformers Under ND Schemes 8135 600 222 8357