| Achievement & Milestones | |||||
| Highlighting efforts made after the formation of CSEB upto April'2011 | |||||
| November 2000 | April 2011 | ||||
| Thermal Generation Capacity | 1240 | MW | 1786 | MW | |
| Hydel Generation Capacity | 120 | MW | 138.70 | MW | |
| Total Generation Capacity (Thermal + Hydel) | 1360 | MW | 1924.70 | MW | |
| Increase in Generation Capacity | 564.70 | MW | |||
| No. of EHT Sub Stations | 27 | 69 | |||
| Length of EHT Line | 5205 | Circuit KM | 8116.30 | Circuit KM | |
| No. of 33/ 11 KV Substations | 248 | 691 | |||
| Length of 33 KV Line | 6988 | Circuit KM | 14853 | Circuit KM | |
| No. of 11/ 0.4 KV Sub Station | 29692 | 69996 | |||
| Length of 11 KV Line | 40556 | KM | 66525 | KM | |
| Length of LT Line | 51314 | KM | 117023 | KM | |
| Capacitor Installed | 94 | MVAR | 934 | MVAR | |
| No. of Electrified Villages | 17953 | 19177 | |||
| Electification percentage | 91.00 | 97.12 | |||
| No. of Electrified Majra Tola | 10375 | 23531 | |||
| No. of Electrified pumps | 72400 | 287108 | |||
| Single Point Connections | 630389 | 1474645 | |||